Why Lift Planning Comes First
Every crane lift you have ever been part of, from a simple pallet of blocks to a tandem lift on a tight city-centre site, should have started in the same place: a plan. It isn’t paperwork for its own sake. Good lift plans are the reason most lifting operations finish without incident, and missing plans are behind many of the accidents that don’t.
If you hold or are working towards a CPCS card in a lifting category (crane operator, slinger signaller, lift supervisor or Appointed Person), you need to know what goes into a lift plan and why each section matters. This guide explains the principles and walks through a practical way to build a plan one section at a time.
“Planning lifting operations is internationally and industry accepted as the most effective tool for producing safe lifting operations.”
The Legal Requirement: LOLER and Beyond
In the UK, the duty to plan comes straight from the Lifting Operations and Lifting Equipment Regulations 1998 (LOLER). Every employer must ensure that every lifting operation involving lifting equipment is:
- Properly planned by a competent person
- Appropriately supervised
- Carried out in a safe manner
LOLER sits alongside the wider duties of the Health and Safety at Work etc. Act 1974 (HASAWA), PUWER 1998 for the equipment itself, and the CDM Regulations 2015 for how the project as a whole is planned and managed. If you need a refresher on how LOLER applies day to day, our guide to LOLER and the lifting regulations every CPCS operator must know goes into more detail.
The same principle applies internationally. In the United States, the ASME P30.1 standard on planning lifting operations was written to prevent or minimise injury and protect life, limb and property. Offshore, the American Petroleum Institute’s Recommended Practice 2D requires the lift team to prepare a lift plan for every lift category. All of these frameworks agree on two things: every lift must be planned, and the person planning it must be competent.
Every lifting operation must also be risk assessed by a competent person. The risk assessment and the lift plan go hand in hand: the assessment identifies the hazards, and the plan sets out how they will be controlled.
Who Is Involved in a Lift Plan?
A lift plan isn’t one person’s document. Several people on the lift team carry responsibility for it:
- The competent or Appointed Person (CPCS A61) writes the plan and is accountable for it
- Reviewers and approvers check the plan and sign it off before work begins
- Crane operators (for example A60 Mobile Crane, A04 Crawler Crane or A02 Tower Crane) must understand the plan and work within its limits
- Slinger signallers (A40) carry out the rigging and communications set out in the plan
- Crane supervisors (A62) make sure the lift is carried out as planned on the day
The plan is only as good as the team’s understanding of it. An operator who has never seen the plan, or a slinger who doesn’t know which lifting points to use, can undo the best planning in seconds. To see how this works on site, read our article on the role of a lift supervisor on a real lifting operation.
Treat the Lift Plan as a Safe System of Work
A lift plan is best understood as a verbal or written description of a safe system of work. That framing matters. It means a plan doesn’t have to be a 40-page document for every lift, but it does have to describe clearly how the lift will be carried out safely.
The most practical way to produce one is to break it into bite-size sections and complete each in turn. That way nothing gets missed and the reviewer can follow your thinking.
The Sections of a Good Lift Plan
A complete lift plan will typically cover the following sections:
- Description of the lift: what is being lifted, from where to where, and why
- Load: weight, dimensions, centre of gravity and any fragile or unstable features
- Load lifting points: which points are designed for lifting, and which are not suitable or safe to use
- Lifting accessories: slings, shackles, spreader beams and their safe working loads
- Rigging: the sling configuration and the angles involved
- Lifting equipment, appliances and machinery: the crane selected, its configuration and its duty chart
- Anchor, fixing or supporting points: outrigger positions, ground bearing capacity and mats
- Additional equipment: tag lines, man-baskets, load cells and similar items
- Lift point, travel route, landing point and surrounding area: obstructions, overhead services and the condition of the landing area
- Lift area control: exclusion zones, barriers and controlling public or worker access
- Environmental conditions: wind speed limits, visibility, lightning and temperature
- Lift team: named roles and the competence of each person
- Communications: radio channels, hand signals and the signaller’s line of sight
- Operational behaviour: the expected conduct and the authority to stop the job
- Step-by-step method statement: the sequence of the lift from start to finish
- Technical drawings, diagrams, photographs or sketches: visual aids for the team
- Lift categorisation: whether the lift is basic, intermediate or complex
- Lift plan administration: authorisation, approval and endorsement signatures
- Toolbox talk: briefing the whole team before the lift
- Lessons learned: recording what went well and what to improve next time
Your workplace may record these in a different order. Reviewers often want to see the lift category and the authorisation signatures first, so many company templates put them at the top. The order matters less than making sure every section has been thought through.
Lifting Points: A Common Test Topic
Identifying which lifting points are not suitable or safe to use is one of the most important skills in lift planning. It also comes up regularly in training and assessment. Loads often have features that look like lifting points but aren’t: transport lugs, tie-down brackets, handles and pipework.
Using the wrong point can overload a fixing, tip the load or drop it completely. The lift plan should name the correct lifting points and state clearly which ones must not be used. Slinger signallers should check this against the load before attaching anything. For more on getting the rigging right, see our guide to slinging and signalling for lifting operations.
Practical Tips from the Field
- Never assume the load weight. Check it against documentation, markings or a load cell. Guesswork is how cranes get overloaded.
- Walk the route. Drawings don’t show the new skip that turned up this morning or the overhead cable that has been rerouted.
- Brief everyone, every time. The toolbox talk is where the plan becomes something the team actually follows.
- If something changes, stop. Weather, ground conditions, the load or the team can all change. A changed lift needs a revised plan.
- Record your lessons learned. Next week’s plan will be better for it.
How CPCS CPD Mastery Fits Into This
Lift planning, LOLER and lifting accessories appear across the CPCS theory tests for crane, slinger signaller, lift supervisor and Appointed Person categories. Whether you are going for your Red Trained Operator card or renewing your Blue Competent Operator card, you need to be confident in this material.
CPCS CPD Mastery gives you 4,000+ practice questions across 43 plant categories, including the lifting categories, so you can revise the topics that actually come up. You also get 5 plant calculators for jobs like working out sling angles and loads, 8 quick reference guides to keep key regulations and hand signals at your fingertips, full mock tests that mirror the real exam, and detailed explanations for every answer so you understand why something is right, not just which option to tap.
Download CPCS CPD Mastery today and make sure your knowledge of lift planning is as solid as the plans you work to on site.